Kibos Sugar and Allied Industries Ltd., Kenya

Our Role: Project consultancy involving engineering & project management sugar plant for expansion & modernization of factory.

Capacity : Expansion from 1800 TCD to 3000 TCD with 15 MW cogeneration.

Providing consultancy for project engineering & complete management involving:

  • Engineering layout as per site conditions.
  • Approval of engineering drawings like GA’s, Layouts, PID’s etc.
  • Follow up and expediting of plant & machinery (P&M).
  • Stage-wise as well as final inspection of P&M.
  • Sequential dispatches of P&M.
  • Follow up for foundation readiness at site as per the sequential dispatches.
  • Supervision of erection & commissioning.

Project highlights:

  • Project divided into two –phases with total duration of 18 months.
  • Phase-1 – completed in Oct 2013 without any production loss in the existing industrial operations.
  • Phase-2 – Oct 2013 to Jan 2015 planned without any loss of production loss; ultimate capacity -3000 TCD with reduction in sugar losses and energy consumption.
  • Plant, fuel & energy balancing done to increase bagasse saving.
  • Product mix – raw, white and refined sugar of EU standards.

 